Duke Energy wins North Carolina approval for major power expansion plan

Duke Energy wins North Carolina approval for major power expansion plan

Regulators advanced plans for new natural gas, solar, battery storage, and nuclear development as the utility prepares for growing electricity demand.

Duke Energy announced Tuesday that North Carolina regulators approved its 2025 Carolinas Resource Plan, advancing the utility’s strategy to expand electricity generation as demand grows across North Carolina and South Carolina.

The North Carolina Utilities Commission’s order, issued Monday, supports the development of 2,300 megawatts of additional solar generation and 2,700 megawatts of battery storage beyond previously approved capacity.

The plan brings total planned solar capacity additions to 8,100 megawatts and battery storage additions to 5,400 megawatts by 2034.

Advertisement

Regulators also advanced plans for 2,720 megawatts of additional combined cycle natural gas capacity and 1,111 megawatts of combustion turbine capacity, expanding the utility’s previously approved generation projects.

The order authorizes continued development work for new nuclear generation, including potential small modular reactors and amendments to existing licensing applications for large reactors in North Carolina and South Carolina.

However, the commission established a separate process to review nuclear technology, financing, costs, and execution risks before approving construction of new nuclear plants.

Duke Energy said the updated resource plan reduces projected customer costs over the next decade by nearly half compared with the plan approved in 2024, following changes in state and federal energy policies.

“We know families and businesses are watching their energy bills closely, and we take that seriously,” said Kendal Bowman, Duke Energy’s North Carolina president.

The utility serves approximately 4.8 million customers across the Carolinas and is investing in new generation and transmission infrastructure to meet growing demand from residential and commercial customers.

Some projects included in the order are already under construction, while others will require additional regulatory review and approval before proceeding.

Disclosure: This article was edited by Vivian Nguyen. For more information on how we create and review content, see our Editorial Policy.