Oracle targets 10GW of AI compute by FY28 as its backlog hits $664 billion

Oracle targets 10GW of AI compute by FY28 as its backlog hits $664 billion

The database giant plans a roughly tenfold capacity jump and says it can fund most of it without heavy new borrowing

Oracle plans to grow its compute capacity from about 1 GW in FY25 to 10 GW by FY28. That is roughly a tenfold expansion in three fiscal years.

The timing matters because Oracle is now near the most expensive stretch of the plan. The company expects capital spending to peak over the next two fiscal years.

The numbers behind the buildout

Oracle laid out the roadmap at its October 2026 investor day. The goal is approximately 10 GW of total AI data center capacity by the end of fiscal 2028.

Around 7 GW of that is expected to come from incremental additions over the coming years. The rest reflects capacity Oracle already has in place or under way.

Oracle’s remaining performance obligations, or RPO, reached $664 billion by the end of the first quarter of FY27.

RPO is contracted revenue that customers have committed to but Oracle has not yet booked. That figure grew 3 to 4-fold year over year, with the company attributing the surge to AI contracts.

Advertisement

In Q1 FY27, Oracle brought online 850 MW of capacity, including more than 300,000 GPUs. Those deployments spanned 38 projects across 11 countries. The previous quarter, the company delivered 400 MW, so output more than doubled in a single quarter.

Some quick arithmetic shows why that pace matters. At 850 MW per quarter, adding roughly 7 GW would take a little over eight quarters, which lines up closely with the FY28 window.

How Oracle plans to pay for it

The company had previously announced it secured over 10 GW of power and data center capacity for the next three years. Most of that is financed through partnerships, customer pre-payments, or bring-your-own-hardware arrangements.

That last model is worth a pause. In a bring-your-own-hardware deal, the customer supplies the chips, and Oracle provides the building, power, and operations around them.

Oracle projects capital expenditures will peak during FY27 and FY28. Free cash flow is expected to turn positive in the second half of FY28.

By FY29, the company expects free cash flow to exceed $30 billion.

On the financing front, Oracle estimates it will need at most $20 billion in additional external financing through FY30. Vendor financing, customer contributions, and pre-payments are meant to cover the remainder.

From software vendor to infrastructure landlord

Oracle is moving away from its traditional enterprise software identity and toward hyperscale data center operations, with AI at the center.

Its role in high-profile collaborations such as the Stargate project with OpenAI places it among the key suppliers of GPU and CPU resources for large AI workloads.

The company’s investor relations messaging points to favorable utilization rates and growing multi-service spending from AI-focused customers as the engine for future self-funding.

What this means

For investors, the story now rests on execution more than demand. A $664 billion backlog suggests customers want the capacity. The open question is whether Oracle can deliver it fast enough to convert those commitments into recognized revenue.

The constraints are physical rather than financial. Oracle still has to navigate power procurement and infrastructure build timelines.

There are a few clean checkpoints to watch. The first is quarterly capacity delivery, and whether Oracle holds or improves on the 850 MW pace. The second is whether capex actually peaks in FY27 and FY28 as projected. The third is whether free cash flow turns positive in the second half of FY28, and whether external financing stays within the $20 billion ceiling through FY30.