Skip to content
Advertisement
Oracle reveals $80B AI infrastructure contract value at Investor Day

Oracle reveals $80B AI infrastructure contract value at Investor Day

Oracle logo on dark (Wikimedia Commons, public domain)

The cloud giant laid out the economics of a roughly 1 GW AI buildout and capped outside financing to calm nervous investors

Oracle Corporation (ORCL) price

Full chart and stats

Loading chart…

Market cap
$437.1B (shares as of 2026-09-07)
P/E (trailing)
22.7 (EPS to 2026-08-31)
Annual revenue
$67.4B USD (FY ended 2026-05-31) 10-K
Annual revenue growth
+17.3% (FY ended 2026-05-31 vs FY ended 2025-05-31) 10-K
Annual net income
17,087,000,000 USD (FY ended 2026-05-31, attributable to the company) 10-K
Annual operating margin
30.6% (FY ended 2026-05-31)
Forward P/E
Unavailable: no dated forecast source

Gloria daily close for session Oct 28, 2026. Market cap and trailing P/E use this close with the SEC share total and trailing diluted earnings, each dated next to its figure. Annual revenue, revenue growth, net income and margin show their own fiscal period and link the 10-K. Current context may postdate this article.

Oracle Corporation and its peers

Company PriceMarket capP/E (trailing)Forward P/EAnnual revenue (USD)Annual revenue growthAnnual net income (USD)Operating margin
Oracle Corporation ORCL · Price dated Oct 28, 2026 · tokenized ORCLx $145$437.1B22.7Unavailable$67.4BFY ended 2026-05-31 · 10-K+17.3%FY ended 2026-05-31 vs 2025-05-31 · 10-K17,087,000,000FY ended 2026-05-31, attributable to the company · 10-K30.6%FY ended 2026-05-31
Palantir Technologies Inc. PLTR · Price dated Oct 28, 2026 · tokenized PLTRx $197$472.9B168.2Unavailable$4.5BFY ended 2025-12-31 · 10-K+56.2%FY ended 2025-12-31 vs 2024-12-31 · 10-K1,625,033,000FY ended 2025-12-31, attributable to the company · 10-K31.6%FY ended 2025-12-31
CrowdStrike Holdings Inc. CRWD · Price dated Oct 28, 2026 · tokenized CRWDx $267$273.0BNot meaningfulLoss, diluted EPS −0.45
to 2026-07-31 · SEC filing
Unavailable$4.8BFY ended 2026-01-31 · 10-K+21.7%FY ended 2026-01-31 vs 2025-01-31 · 10-K−162,502,000FY ended 2026-01-31, attributable to the company · 10-K−6.1%FY ended 2026-01-31
Shopify Inc. SHOP · Price dated Oct 28, 2026 $168Unavailable113.7Unavailable$11.6BFY ended 2025-12-31 · 10-K+30.1%FY ended 2025-12-31 vs 2024-12-31 · 10-K1,231,000,000FY ended 2025-12-31, attributable to the company · 10-K12.7%FY ended 2025-12-31

Missing figures stay unavailable. Forward P/E requires a dated source. Annual revenue, revenue growth, net income and margin come from each company's own 10-K, in US dollars, and each row shows that fiscal year. Revenue growth compares the fiscal year with the prior year stated in the same 10-K. Net income is the full year amount attributable to the company, or available to common stockholders where the filing states only that, or consolidated net income. Each row names its basis. Trailing P/E reads "Not meaningful" when the dated trailing diluted EPS is a loss or zero. An operating margin appears only when the filing states both the operating income and the revenue for the same year.

Sources: SEC filings, Gloria daily closes and CoinGecko. Oldest record refresh: Oct 28, 2026, 5:41 PM EDT. Refresh is not a price or filing date. Each row shows its price date and its annual fiscal period. Peers use industry code and company size, or editorial selection. Market cap multiplies that row price by the company share total the latest SEC filing states for every share class together. Trailing P/E divides it by trailing diluted earnings from SEC filings. Rolled earnings per share are approximate because share counts can change between periods. Both appear only when the SEC data carries its date, so they are estimates at one price date, not synchronized filing valuations. Not investment advice.

Oracle finally showed investors the spreadsheet behind its AI data center spree. At its Investor Day on October 28, 2026, the company disclosed that a large AI infrastructure contract carries approximately $80 billion in remaining performance obligations (RPO).

RPO is contracted revenue that a customer has committed to but Oracle has not yet booked. Think of it as a signed lease where the rent checks haven’t arrived.

The market liked what it heard. Oracle shares jumped by roughly 11 to 13% on the day as financing concerns eased.

The math behind one gigawatt

The headline contract comes with an estimated total capital expenditure of around $37 billion. That is what Oracle expects to spend building the infrastructure before the revenue arrives.

Once fully ramped, the buildout is anticipated to bring in roughly $16 billion in annual revenue. That revenue level corresponds to a capacity scale of about 1 gigawatt (GW).

Oracle expects these contracts to run for an average of five years. The company is targeting a gross margin of approximately 35% and an operating margin of around 34%.

Advertisement

The bigger number for investors may be the return. Oracle projects a return on investment of approximately 28%, alongside 100% free cash flow (FCF) conversion once the initial construction phase wraps up.

Financing guardrails and bigger targets

Oracle’s answer was a cap. The company committed to limiting external financing for AI projects to $20 billion, split between debt and equity, through fiscal year 2030.

The longer-range targets were ambitious. Oracle anticipates reaching total AI capacity of about 10 GW by the end of fiscal year 2028.

On cash flow, the company expects to turn FCF positive in the second half of FY28. It then targets more than $30 billion in free cash flow in FY29.

Revenue goals were even bigger. Oracle aims for total revenue above $225 billion by FY30, which reflects a compound annual growth rate of more than 35%.

Background: a backlog built on AI demand

The Investor Day numbers sit on top of an already enormous backlog. Oracle’s total RPO climbed to $664 billion in the first quarter of FY27.

That same quarter, the company reported 850 megawatts of capacity. The jump from 850 MW toward a 10 GW target by the end of FY28 gives a sense of how steep the planned ramp is.

Much of the demand traces back to Oracle’s strategic partnership with OpenAI. That relationship has become a key driver of the company’s AI infrastructure orders.

What this means

For shareholders, the most important shift is from vague promises to measurable unit economics. Oracle has now given investors a model: roughly $37 billion in, roughly $16 billion a year out at full ramp, with about a 28% ROI over contracts averaging five years.

The $20 billion external financing cap addresses the core investor worry head on, but it also boxes Oracle in. If construction costs run over or customers ramp more slowly, the company has committed to not simply borrowing its way through the gap.

RPO growth remains the cleanest leading indicator. If that $664 billion backlog keeps expanding and converts into recognized revenue on time, the FY29 cash flow target looks more credible.

Disclosure: This article was edited by Diego Almada Lopez. For more information on how we create and review content, see our Editorial Policy.

More in Technology

See all
Previous storyCashu introduces physical tap-to-pay card for offline Bitcoin ecash payments