Anthropic-anchored Queensland data center draws 595 objections
Anthropic / Wikimedia Commons (Public domain)
Nearly every public submission on the Western Downs Digital Park opposed the project, citing water, power prices, noise and housing pressure
Anthropic wanted a home for its AI ambitions in rural Queensland. Most of the locals who weighed in would prefer it found one somewhere else.
A project filing for the Western Downs Digital Park shows that 595 of the nearly 600 public submissions lodged by the November 11 deadline opposed the development. Anthropic, the company behind the Claude language model, signed on as the campus’s anchor tenant in mid-September 2026.
A very large building on very old farmland
The proposed campus is not a modest server room tucked behind a shopping center. Plans call for four buildings with a total planned IT computing load of 1.44 gigawatts (GW).
Peak power draw is pegged even higher, at 2.16 GW. IT load is the electricity the computers themselves consume. The larger peak figure covers the full facility at maximum demand, which is where things like cooling come in.
The project would sit on a 725-hectare site of former farmland near Dalby, roughly 250 km from Brisbane.
The complaints in the filing cover a familiar list for anyone tracking data center fights:
AI, tech, and the markets they move—in one daily briefing.
Daily. Free. Join 34,000+ readers across crypto, finance, and policy.
- Water use, a sensitive subject in agricultural regions
- Electricity pricing, with residents worried about the knock-on effect on their own bills
- Noise from the operating facility
- Construction traffic during the build phase
- Housing pressure as workers arrive in the area
One-third of the objections came from people living within 200 km of the site. The remainder came from farther away.
The Anthropic effect
Local resistance did not start at full volume. According to the research findings, opposition intensified sharply after Anthropic was announced as the lease tenant.
Timing has not helped keep the profile low either. Anthropic’s commitment to an Australian data presence lines up with its Wall Street IPO, which valued the company at around $1.5 trillion on November 18, 2026.
Part of a broader Australian pattern
The Western Downs fight is not happening in isolation. Community opposition to data center projects has been building across Australia in 2026, with several proposals withdrawn or delayed amid similar worries about environmental impact and resource use.
What happens next
The submissions themselves are non-binding. Nobody gets to cancel the project by filling out a form, and 595 objections do not amount to a veto.
They do, however, carry weight. The public input could influence approvals and change the project’s trajectory, particularly as local and government authorities work through the assessments the development needs.
For now, the numbers from the consultation are clear. Of the nearly 600 people who took the time to write in, 595 said no.
Disclosure: This article was edited by Diego Almada Lopez. For more information on how we create and review content, see our Editorial Policy.