JERA plans AI data centers beside its power plants with Dell and RHAELM

JERA plans AI data centers beside its power plants with Dell and RHAELM

Japan's largest power generator wants to put AI compute next to its turbines, starting with a 400 MW site in Chiba

JERA, Japan’s biggest power generator, wants AI data centers built right next to its power plants. The company reportedly plans to build these facilities for Anthropic and Meta at its generation sites.

The idea is simple. Instead of hauling electricity across a congested grid to a data center, you put the data center where the electricity is made. Getting a power hookup can take years in this industry, so skipping that step could be worth a lot of money.

The Chiba blueprint

The framework took shape on October 1, 2026. On that date, JERA signed a memorandum of understanding with Dell Technologies and UK-based developer RHAELM to develop large-scale AI data centers co-located with power plants.

The first target is JERA’s Chiba Thermal Power Station, an LNG-fired plant with output of approximately 4.38 GW.

The planned data center there would have 400 MW of capacity. That makes it a hyperscale facility, though it would use only a slice of what the plant can produce.

The partners expect total investment for the Chiba project to exceed $15 billion (¥2.3 trillion). Operations are slated to begin in phases starting around 2028, with full capacity targeted for 2029.

Advertisement

Each partner has a defined role:

  • JERA supplies the land and the power.
  • RHAELM handles development, construction, operation and financing.
  • Apollo Global Management is positioned as RHAELM’s financing partner.
  • Dell Technologies provides standardized rack-scale AI infrastructure.

Why behind-the-meter matters

The key technical feature is a behind-the-meter power setup. The data center draws electricity directly from the plant rather than through the public grid.

For data centers, that queue is the grid connection. Securing a new interconnection can be slow, and AI developers want capacity now. Co-locating with an existing plant lets the partners move faster than they could if they waited for new grid capacity.

A 2028 phased start is aggressive for a facility of this size, and the behind-the-meter model is what makes that timeline plausible.

Background: who JERA is

JERA is Japan’s largest power generation company and a major LNG trader, with a generation business that long predates the AI boom.

The company generates roughly one-third of Japan’s electricity. It also supplies nearly all the power in the Tokyo area.

JERA’s broader investment plans through 2035 focus on LNG, renewables and hydrogen and ammonia. The data center push now sits alongside those energy plans.

The company is also reviewing how to pay for all of this. JERA is exploring expanded funding strategies, potentially including an IPO, to keep pace with rising AI power demand.

The Chiba facility is meant to be a prototype rather than a one-off. The partners aim to scale AI data centers to multiple gigawatts across various JERA thermal sites in Japan during the 2030s.

What this means

JERA’s model reverses the usual relationship between utilities and tech companies. Normally a utility sells power into the grid and customers buy from it. Here, the utility acts more like a landlord whose property comes with its own power supply.

The fuel source matters too. Chiba runs on LNG, so this AI capacity would be powered by natural gas rather than renewables. JERA’s long-term plans include renewables and hydrogen and ammonia, but the first project is tied to a fossil fuel plant.

Funding is another open question. A project topping $15 billion is a large bet even with Apollo involved. JERA’s openness to options like an IPO suggests the company expects its capital needs to grow fast if the multi-gigawatt plan moves forward.

Execution risk is real. The deal is currently a memorandum of understanding, not a finished facility. Timelines of 2028 and 2029 leave room for delays in construction, equipment delivery or financing.

Disclosure: This article was edited by Diego Almada Lopez. For more information on how we create and review content, see our Editorial Policy.